Carden-Heidi-Little is a gas well in Tarrant County, Texas, operated by Tep Barnett USA, LLC in the Newark, East (Barnett Shale) field.

1 well

395,775mcf gas, last 12 months−12% vs prior year
RRC lease
09-287689

Is your check right?

Check my statement

Where it sits

This county

Tarrant CountyTarrantWiseHoodEllisCollinDallasParkerJohnsonDentonTarrant County
Tarrant County
Gas in Jul 2026
35,127 mcf
Reporting since
Jan 2020

Production by month

Gas output fell 12% over the last 12 months

  • Gas (bars)
  • Last 12 months
Gas output fell 12% over the last 12 monthsMonthly gas production for CARDEN-HEIDI-LITTLE, Aug 2023 to Jul 2026. Gas output fell 12% over the last 12 months. 395,775 mcf in the 12 months through Jul 2026, against 452,131 mcf in the 12 months before.Last 12 months: 395,775 mcfmcf per month020k40k60k80kOct 23Jan 24AprJulOctJan 25AprJulOctJan 26AprJul
Gas output fell 12% over the last 12 monthsMonthly gas production for CARDEN-HEIDI-LITTLE, Aug 2023 to Jul 2026. Gas output fell 12% over the last 12 months. 395,775 mcf in the 12 months through Jul 2026, against 452,131 mcf in the 12 months before.Last 12 monthsmcf per month020k40k60k80kJan 24JulJan 25JulJan 26Jul

SourceTexas Railroad Commission Production Data Query, through Jul 2026.

Where the gas went

All of the gas went to a transmission line in the last 12 months

All of the gas went to a transmission line in the last 12 monthsShare of CARDEN-HEIDI-LITTLE gas by disposition code each month, Aug 2023 to Jul 2026. All of the gas went to a transmission line in the last 12 months.Share of the lease’s gas by disposition code, per month0%50%100%Oct 23Jan 24AprJulOctJan 25AprJulOctJan 26AprJul
All of the gas went to a transmission line in the last 12 monthsShare of CARDEN-HEIDI-LITTLE gas by disposition code each month, Aug 2023 to Jul 2026. All of the gas went to a transmission line in the last 12 months.Share of gas by disposition code0%50%100%Jan 24JulJan 25JulJan 26Jul

SourceTexas Railroad Commission Production Data Query, through Jul 2026.

1 well on this lease

Wells on CARDEN-HEIDI-LITTLE
API numberWell no.Status
42-439-371672HActive

SourceTexas Railroad Commission Wellbore Query.

Buyers and gatherers

Companies named on the Form P-4, by product
CompanyProductRoleShare%From
Total Gas & Power Na, Inc.Gas-well gasBuys100Jun 8, 2019
Williams Mlp Operating LLCGas-well gasGathers100Jun 8, 2019

SourceRailroad Commission Form P-4 file, Sep 24, 2026 (source).

166.24 acres on the newest permit

  • Worth asking

    An allocation well is on this lease

    A well drilled across several tracts shares its production by an allocation formula, so the decimal is not always your acres over the unit acres. Ask the operator for the allocation formula and the tract factor for your land.

  • Worth asking

    A Rule 37 case is listed

    The RRC permit records list a Rule 37 case. This does not establish your royalty share. Ask for the permit and unit plat for your well.

Check your decimal on this lease
Permits for Carden-Heidi-Little
API numberWell no.Acreson the permit
42-439-371672H166.24

SourceRailroad Commission drilling permits, Oct 3, 2026 (source 1, source 2).

Estimate your royalty

36 months, newest first

Ledger for CARDEN-HEIDI-LITTLE
MonthGas producedmcfGas soldmcf, codes 2+3FlaredmcfWTI$/bblHenry Hub$/MMBtu
Jul 202635,12735,1270$80.46$2.89
Jun 202634,75034,7500$84.81$3.15
May 202636,69536,6950$102.13$2.94
Apr 202635,08335,0830$100.32$2.77
Mar 202633,86333,8630$91.38$3.04
Feb 202626,86626,8660$64.51$3.62
Jan 202630,75130,7510$60.04$7.72
Dec 202530,82930,8290$57.97$4.26
Nov 202531,45431,4540$60.06$3.79
Oct 202533,12633,1260$60.89$3.19
Sep 202533,44633,4460$63.96$2.97
Aug 202533,78533,7850$64.86$2.91
Jul 202535,68835,6880$68.39$3.20
Jun 202534,75834,7580$68.17$3.02
May 202536,62636,6260$62.17$3.12
Apr 202536,03436,0340$63.54$3.42
Mar 202537,78937,7890$68.24$4.12
Feb 202534,62034,6200$71.53$4.19
Jan 202538,75938,7590$75.74$4.13
Dec 202438,28938,2890$70.12$3.01
Nov 202437,01937,0190$69.95$2.12
Oct 202440,47640,4760$71.99$2.20
Sep 202440,46940,4690$70.24$2.28
Aug 202441,60441,6040$76.68$1.99
Jul 202443,55943,5590$81.80$2.07
Jun 202440,53840,5380$79.77$2.54
May 202443,00543,0050$80.02$2.12
Apr 202438,57938,5790$85.35$1.60
Mar 202441,05841,0580$81.28$1.49
Feb 202440,22440,2240$77.25$1.72
Jan 202444,52844,5280$74.15$3.18
Dec 202346,13846,1380$71.90$2.52
Nov 202345,66345,6630$77.69$2.71
Oct 202348,01048,0100$85.64$2.98
Sep 202347,34247,3420$89.43$2.64
Aug 202350,00650,0060$81.39$2.58

SourceTexas Railroad Commission Production Data Query, through Jul 2026. Prices: EIA, through Aug 2026. Updated Oct 2, 2026.

How to check your stub against this lease Checks stopped on this lease? See the likely reasons

Do your checks match this lease?

Nearby

Tep Barnett USA, LLC in Tarrant County

All Tep Barnett USA, LLC leases →

Newark, East (Barnett Shale) field

All leases in this field →

Leases within 10 km

Drilling permits within 10 km