Skip to content
Royalty Clerk

Texas gas well

Producing

SILVER HAMMER - SADIE B

Silver Hammer - Sadie B is a gas well in Nacogdoches County, Texas, operated by Adamas Energy LLC in the Carthage (Haynesville Shale) field.

1 well

3,907,861mcf gas, last 12 months−56% vs prior year
RRC lease
06-296958

Is your check right?

Check my statement

Where it sits

This county

Nacogdoches CountyNacogdochesPanolaSan AugustineShelbyRuskAngelinaCherokeeNacogdoches County
Nacogdoches County
Gas in Jul 2026
197,001 mcf
Reporting since
Jul 2024

Checks stopped on this lease?

  • Operator

    Operator changed: Adamas Energy LLC took over from Aethon Energy Operating LLC in Mar 2026.

SourceRailroad Commission production, P-5 and P-4 records, data through Jul 2026.

See why checks stop on this lease

Production by month

Gas output fell 56% over the last 12 months

  • Gas (bars)
  • Last 12 months
Gas output fell 56% over the last 12 monthsMonthly gas production for SILVER HAMMER - SADIE B, Jul 2024 to Jul 2026. Gas output fell 56% over the last 12 months. 3,907,861 mcf in the 12 months through Jul 2026, against 8,807,540 mcf in the 12 months before.Last 12 months: 3,907,861 mcfmcf per month0250k500k750k1MJul 24OctJan 25AprJulOctJan 26AprJul
Gas output fell 56% over the last 12 monthsMonthly gas production for SILVER HAMMER - SADIE B, Jul 2024 to Jul 2026. Gas output fell 56% over the last 12 months. 3,907,861 mcf in the 12 months through Jul 2026, against 8,807,540 mcf in the 12 months before.Last 12 monthsmcf per month0250k500k750k1MJul 24Jan 25JulJan 26Jul

SourceTexas Railroad Commission Production Data Query, through Jul 2026.

Where the gas went

Over 99% of the gas went to a transmission line in the last 12 months

  • Transmission line (2)
  • Lease fuel (1)
Over 99% of the gas went to a transmission line in the last 12 monthsShare of SILVER HAMMER - SADIE B gas by disposition code each month, Jul 2024 to Jul 2026. Over 99% of the gas went to a transmission line in the last 12 months.Share of the lease’s gas by disposition code, per month0%50%100%Jul 24OctJan 25AprJulOctJan 26AprJul
Over 99% of the gas went to a transmission line in the last 12 monthsShare of SILVER HAMMER - SADIE B gas by disposition code each month, Jul 2024 to Jul 2026. Over 99% of the gas went to a transmission line in the last 12 months.Share of gas by disposition code0%50%100%Jul 24Jan 25JulJan 26Jul

SourceTexas Railroad Commission Production Data Query, through Jul 2026.

  • Transmission line (2)

    100% · 3,896,598 mcf

  • Lease fuel (1)

    0.3% · 11,263 mcf

Who has run this lease

The operator changed once, most recently in Mar 2026

Operators of this lease over timeAethon Energy Operating LLC, Jul 2024 to Feb 2026; Adamas Energy LLC, Mar 2026 to Jul 202620252026Changed Mar 2026Aethon Energy Operating LLCJul 2024 to Feb 2026Adamas Energy LLCMar 2026 to now
Operators of this lease over timeAethon Energy Operating LLC, Jul 2024 to Feb 2026; Adamas Energy LLC, Mar 2026 to Jul 202620252026Changed Mar 2026Aethon Energy Operating LLCJul 2024 to Feb 2026Adamas Energy LLCMar 2026 to now

SourceTexas Railroad Commission Production Data Query, through Jul 2026.

1 well on this lease

Wells on SILVER HAMMER - SADIE B
API numberWell no.Status
42-347-335003HActive

SourceTexas Railroad Commission Wellbore Query.

Buyers and gatherers

Companies named on the Form P-4, by product
CompanyProductRoleShare%From
Scona LLCGas-well gasBuys100Jul 1, 2024
Kudu Midstream LLCGas-well gasGathers100Jul 1, 2024

SourceRailroad Commission Form P-4 file, Sep 24, 2026 (source).

1,868.21 acres on the newest permit

  • Worth asking

    An allocation well is on this lease

    A well drilled across several tracts shares its production by an allocation formula, so the decimal is not always your acres over the unit acres. Ask the operator for the allocation formula and the tract factor for your land.

  • Worth asking

    A Rule 37 case is listed

    The RRC permit records list a Rule 37 case. This does not establish your royalty share. Ask for the permit and unit plat for your well.

Check your decimal on this lease
Permits for Silver Hammer - Sadie B
API numberWell no.Acreson the permit
42-347-335003H1,868.21

SourceRailroad Commission drilling permits, Oct 3, 2026 (source 1, source 2).

Estimate your royalty

25 months, newest first

Ledger for SILVER HAMMER - SADIE B
MonthGas producedmcfGas soldmcf, codes 2+3FlaredmcfWTI$/bblHenry Hub$/MMBtu
Jul 2026Adamas Energy197,001196,4790$80.46$2.89
Jun 2026Adamas Energy204,831204,3260$84.81$3.15
May 2026Adamas Energy231,150230,1060$102.13$2.94
Apr 2026Adamas Energy244,513243,5030$100.32$2.77
Mar 2026Adamas Energy275,132274,0880$91.38$3.04
Feb 2026Aethon Energy270,720269,7780$64.51$3.62
Jan 2026Aethon Energy323,951322,9070$60.04$7.72
Dec 2025Aethon Energy360,409359,3650$57.97$4.26
Nov 2025Aethon Energy385,097384,0870$60.06$3.79
Oct 2025Aethon Energy437,006435,9620$60.89$3.19
Sep 2025Aethon Energy464,900463,8900$63.96$2.97
Aug 2025Aethon Energy513,151512,1070$64.86$2.91
Jul 2025Aethon Energy558,454557,4100$68.39$3.20
Jun 2025Aethon Energy566,850565,8400$68.17$3.02
May 2025Aethon Energy638,661637,6170$62.17$3.12
Apr 2025Aethon Energy651,415651,4150$63.54$3.42
Mar 2025Aethon Energy726,479726,4790$68.24$4.12
Feb 2025Aethon Energy696,664696,6640$71.53$4.19
Jan 2025Aethon Energy802,696802,6960$75.74$4.13
Dec 2024Aethon Energy824,600824,6000$70.12$3.01
Nov 2024Aethon Energy842,837842,8370$69.95$2.12
Oct 2024Aethon Energy815,342815,3420$71.99$2.20
Sep 2024Aethon Energy842,257842,2570$70.24$2.28
Aug 2024Aethon Energy841,285841,2850$76.68$1.99
Jul 2024Aethon Energy817,564817,5640$81.80$2.07

SourceTexas Railroad Commission Production Data Query, through Jul 2026. Prices: EIA, through Aug 2026. Updated Oct 2, 2026.

How to check your stub against this lease Checks stopped on this lease? See the likely reasons

Do your checks match this lease?

Nearby

Adamas Energy LLC in Nacogdoches County

All Adamas Energy LLC leases →

Carthage (Haynesville Shale) field

All leases in this field →

Leases within 10 km

Drilling permits within 10 km