Skip to content
Royalty Clerk

Texas gas well

Producing

HARMAN UNIT

Harman Unit is a gas well in Shelby County, Texas, operated by XTO Energy Inc. in the Huxley (6100) field.

1 well

22,309mcf gas, last 12 months0% vs prior year
RRC lease
06-185087

Is your check right?

Check my statement

Where it sits

This county

Shelby CountyShelbyPanolaSan AugustineNacogdochesSabineRuskShelby County
Shelby County
Gas in Jul 2026
1,496 mcf
Reporting since
Jan 2020

Production by month

Gas output held steady over the last 12 months

  • Gas (bars)
  • Last 12 months
Gas output held steady over the last 12 monthsMonthly gas production for HARMAN UNIT, Aug 2023 to Jul 2026. Gas output held steady over the last 12 months. 22,309 mcf in the 12 months through Jul 2026, against 22,252 mcf in the 12 months before.Last 12 months: 22,309 mcfmcf per month01,0002,0003,0004,000Oct 23Jan 24AprJulOctJan 25AprJulOctJan 26AprJul
Gas output held steady over the last 12 monthsMonthly gas production for HARMAN UNIT, Aug 2023 to Jul 2026. Gas output held steady over the last 12 months. 22,309 mcf in the 12 months through Jul 2026, against 22,252 mcf in the 12 months before.Last 12 monthsmcf per month01,0002,0003,0004,000Jan 24JulJan 25JulJan 26Jul

SourceTexas Railroad Commission Production Data Query, through Jul 2026.

Where the gas went

91% of the gas went to a transmission line in the last 12 months

  • Processing plant (3)
  • Transmission line (2)
  • Lease fuel (1)
91% of the gas went to a transmission line in the last 12 monthsShare of HARMAN UNIT gas by disposition code each month, Aug 2023 to Jul 2026. 91% of the gas went to a transmission line in the last 12 months.Share of the lease’s gas by disposition code, per month0%50%100%Oct 23Jan 24AprJulOctJan 25AprJulOctJan 26AprJul
91% of the gas went to a transmission line in the last 12 monthsShare of HARMAN UNIT gas by disposition code each month, Aug 2023 to Jul 2026. 91% of the gas went to a transmission line in the last 12 months.Share of gas by disposition code0%50%100%Jan 24JulJan 25JulJan 26Jul

SourceTexas Railroad Commission Production Data Query, through Jul 2026.

  • Transmission line (2)

    91% · 20,241 mcf

  • Lease fuel (1)

    7.8% · 1,750 mcf

  • Processing plant (3)

    1.4% · 318 mcf

1 well on this lease

Wells on HARMAN UNIT
API numberWell no.Status
42-419-307451Active

SourceTexas Railroad Commission Wellbore Query.

Buyers and gatherers

Companies named on the Form P-4, by product
CompanyProductRoleShare%FromUntil
Eastex Crude Company, LLCCondensateGathers100Jan 1, 2023–
Xto Energy Inc.Gas-well gasBuys100Dec 1, 2008–
Xto Energy Inc.Gas-well gasGathers100Dec 1, 2008–
Eastex Crude CompanyCondensateGathers100Nov 3, 2000Jan 1, 2023

SourceRailroad Commission Form P-4 file, Sep 24, 2026 (source).

694.70 acres on the newest permit

A pooling certificate was filed

Permits for Harman Unit
API numberWell no.Acreson the permit
42-419-307451694.70

SourceRailroad Commission drilling permits, Sep 26, 2026 (source 1, source 2).

Estimate your royalty

36 months, newest first

Ledger for HARMAN UNIT
MonthGas producedmcfGas soldmcf, codes 2+3FlaredmcfWTI$/bblHenry Hub$/MMBtu
Jul 20261,4961,4790$80.46$2.89
Jun 20261,4911,4750$84.81$3.15
May 20261,5121,4970$102.13$2.94
Apr 20261,6971,6830$100.32$2.77
Mar 20261,6561,6420$91.38$3.04
Feb 20261,7081,6970$64.51$3.62
Jan 20262,1672,1200$60.04$7.72
Dec 20252,3752,0940$57.97$4.26
Nov 20252,1111,7930$60.06$3.79
Oct 20252,3831,9130$60.89$3.19
Sep 20251,8251,5520$63.96$2.97
Aug 20251,8881,6140$64.86$2.91
Jul 20251,9571,6640$68.39$3.20
Jun 20252,3582,0380$68.17$3.02
May 20251,9811,7570$62.17$3.12
Apr 20251,3981,2540$63.54$3.42
Mar 20251,6951,6230$68.24$4.12
Feb 20251,8141,7370$71.53$4.19
Jan 20252,0451,9560$75.74$4.13
Dec 20242,1252,0340$70.12$3.01
Nov 20242,0881,9980$69.95$2.12
Oct 20241,7481,6730$71.99$2.20
Sep 20241,5451,4780$70.24$2.28
Aug 20241,4981,4330$76.68$1.99
Jul 20241,8031,7250$81.80$2.07
Jun 20241,8421,7620$79.77$2.54
May 20242,3962,2930$80.02$2.12
Apr 20242,1452,0530$85.35$1.60
Mar 20242,7552,6380$81.28$1.49
Feb 20242,9432,8170$77.25$1.72
Jan 20242,0621,9720$74.15$3.18
Dec 20231,6971,6240$71.90$2.52
Nov 20231,9531,8690$77.69$2.71
Oct 20231,5321,4660$85.64$2.98
Sep 20231,3671,3080$89.43$2.64
Aug 20231,5841,5160$81.39$2.58

SourceTexas Railroad Commission Production Data Query, through Jul 2026. Prices: EIA, through Aug 2026. Updated Sep 28, 2026.

How to check your stub against this lease

Do your checks match this lease?

Nearby

XTO Energy Inc. in Shelby County

All XTO Energy Inc. leases →

Huxley (6100) field

All leases in this field →

Leases within 10 km

Drilling permits within 10 km