Texas gas wellRRC 06-265294Producing
Julia Gu
One well on 669 acres in Nacogdoches County. The lease produced 211,868 thousand cubic feet of gas in the last 12 months, through August 2026.
- Operator
- Adamas Energy LLC
- County
- Nacogdoches
- On record since
- July 2012
- Newest report on file
- August 2026
- Unit on the newest permit
- 669 acres
Outline: the original land surveys this lease's wells sit in. The State publishes no lease outlines. RRC surveys, 2026-09-29.
The story, from 170 monthly reports
2012 to 2026: it sold the most in 2022
July 2012: the first month the lease sold gas on record, 66,953 thousand cubic feet.
November 2017: Aethon Energy Operating LLC took over from Rockcliff Energy Operating LLC.
February 2022 to June 2022: five months in a row with no oil and no gas reported.
2022: the year the lease sold the most, $8.07 million of oil and gas at public prices.
March 2026: Adamas Energy LLC took over from Aethon Energy Operating LLC.
August 2026 is the newest monthly production report on file.
SourceRailroad Commission production reports, July 2012 through August 2026. Not a forecast, not reserves.
Checks stopped on this lease?
Operator changed: Adamas Energy LLC took over from Aethon Energy Operating LLC in Mar 2026.
SourceRailroad Commission production, P-5 and P-4 records, data through August 2026.See why checks stop on this lease
170 months against 7 other recordsNew
Every month since July 2012, and what else happened that month
The lease is the line on top. Under it, on the same clock: the weather, the State, the price, the wells next door, who ran the lease, who bought from it and the rest of the field. Move across it.
Gas averaged $7.72 an mcf · Aethon Energy Operating LLC
- WeatherWinter storm, January 24 to 25. Three days below 20°F in Nacogdoches County. Cold, January 24 to 27. Three days below 20°F in Nacogdoches County.
Move the pointer or drag across the chart. The numbered buttons jump to each drop.
Monthly gas sold from this lease since July 2012, with seven record tracks beneath it. Use the left and right arrow keys to move month by month.. 170 months from July 2012 to August 2026. The most in one month: 227,828 mcf, October 2022. The newest month: 10,821 mcf. 6 months with nothing reported. Moments marked: 1, Mar 2014; 2, Jan 2023; 3, Mar 2023; 4, Feb 2024; 5, Dec 2024; 6, Jan 2025; 7, Dec 2025; 8, Jan 2026.
SourcesProduction, cut-offs, operators and buyers: Railroad Commission of Texas. Weather: NOAA. Prices: U.S. Energy Information Administration. Fracs: FracFocus. A record in the same month is not proof of a cause. Through August 2026.
Royalty Watch tells you the month a drop starts, with the records from that month.Watch this lease
167 months, one line eachNew
Five months of silence in 2022
A gap is a month with no oil and no gas reported. Many leases end after 60 to 90 days without production unless the lease says otherwise.
months in a row with nothing reported, February to June 2022. Reports are on file for all 5 months, with no oil and no gas. The only silence on record here.
thousand cubic feet of gas on the newest report on file with oil or gas, for August 2026, the State's newest month.
of 167 months with oil or gas reported since July 2012.
thousand cubic feet of gas a day on average from September 2025 through August 2026, counting a month with no report on file as zero.
A shut-in payment or work on the wells can keep a lease alive through a gap. Your own lease paper decides.
SourceRailroad Commission production reports, July 2012 through May 2026. The newest months, after May 2026, are left out of the count because reports arrive late.
Royalty Watch tells you when a silent month starts, and drafts the letter asking whether the lease is still in force.Watch this lease
15 years of state records, 2012 to 2026
Sold since July 2012
$19.9million
Sales at public prices before tax and deductions. Multiply by your decimal interest to estimate your share.
- Gas sold
- 5,086,124thousand cubic feet
- Best year
- 2022$8.07 million sold
| Year | Oil, dollars | Gas, dollars | Total |
|---|---|---|---|
| 2012 | $0 | $2.09 million | $2.09 million |
| 2013 | $0 | $2.7 million | $2.7 million |
| 2014 | $0 | $1.08 million | $1.08 million |
| 2015 | $0 | $372,000 | $372,000 |
| 2016 | $0 | $236,000 | $236,000 |
| 2017 | $0 | $208,000 | $208,000 |
| 2018 | $0 | $149,000 | $149,000 |
| 2019 | $0 | $118,000 | $118,000 |
| 2020 | $0 | $90,000 | $90,000 |
| 2021 | $0 | $172,000 | $172,000 |
| 2022 | $0 | $8.07 million | $8.07 million, sold the most |
| 2023 | $0 | $2.63 million | $2.63 million |
| 2024 | $0 | $767,000 | $767,000 |
| 2025 | $0 | $902,000 | $902,000 |
| 2026, 2026 so far | $0 | $351,000 | $351,000 |
Did a relative own a share of this lease?
SourcesRailroad Commission Production Data Query, every monthly report since July 2012. EIA monthly WTI and Henry Hub prices. 2026 is part of a year, drawn lighter. Not a forecast, not reserves.
Who has run this lease
The operator changed three times, most recently in March 2026
The company named on each monthly report to the State. The operator is not always the company that pays.
- Adamas Energy LLCMarch 2026 to now
- Aethon Energy Operating LLCNovember 2017 to February 2026
- Rockcliff Energy Operating LLCOctober 2017 to October 2017
- Operator number 744737July 2012 to September 2017
SourcesRailroad Commission production reports, the operator on each month’s report, July 2012 through August 2026.
The newest well, seen from the side
No well on the way. Well 1H was completed in April 2012.
- Permit filedNot on file
- Drilling startedNot on file
- FrackedNot on file
- Completion filedApril 4, 2012
- First production on the leaseNot on file
- First checkNot on file
SourcesRailroad Commission drilling permits and well records, and the FracFocus registry. Lease record built November 17, 2026.
Royalty Watch follows new well permits and completions on this lease.Watch this lease
About 6 miles across
Wells on this lease and around it
For a lawyer, a buyer or a probate file. Wells and permits within about 2 miles. Railroad Commission of Texas, FracFocus and USGS imagery.
From the State's well records
One well on this lease
| Well | API number | Completed | Sidewaysfeet | Depthfeet | Today |
|---|---|---|---|---|---|
| 1H | 42-347-33307 | April 2012 | 5,412 | 13,931 | Active |
SourceRailroad Commission wellbore and completion records.
What the drilling permits say
669acres on the newest permit
- 669 acres, on the 2012 permits
A Rule 37 case is listed The RRC permit records list a Rule 37 case. This does not establish your royalty share. Ask for the permit and unit plat for your well.
Gas, August 2026, dollars per thousand cubic feet New
Four prices for the same gas
What the market paid, what the operator told its investors, what it told the tax office for this lease, and the one only you hold.
No lower tax approval on file
- Usual gas rate
- 7.50%
No lower tax approval appears for this lease in the two years covered by the Comptroller’s list as of October 1, 2026.
Estimate your royalty
Type the decimal from your division order
The starting decimal is an example. Nothing you type here leaves this page.
$246a month
At these prices the whole lease’s reported sales were about $756,000 over 12 reported months. Your estimated share is $2,950 before taxes and deductions.
Monthly owner volumes and values
| Month | Oil (bbl) | Oil value | Gas (mcf) | Gas value | Total |
|---|---|---|---|---|---|
| August 2026 | 0 | $0.00 | 42.2695 | $117.51 | $117.51 |
| July 2026 | 0 | $0.00 | 42.0977 | $121.66 | $121.66 |
| June 2026 | 0 | $0.00 | 39.8633 | $125.57 | $125.57 |
| May 2026 | 0 | $0.00 | 44.5469 | $130.97 | $130.97 |
| April 2026 | 0 | $0.00 | 45.8828 | $127.10 | $127.10 |
| March 2026 | 0 | $0.00 | 50.6797 | $154.07 | $154.07 |
| February 2026 | 0 | $0.00 | 49.2344 | $178.23 | $178.23 |
| January 2026 | 0 | $0.00 | 54.0508 | $417.27 | $417.27 |
| December 2025 | 0 | $0.00 | 63.875 | $272.11 | $272.11 |
| November 2025 | 0 | $0.00 | 135.7461 | $514.48 | $514.48 |
| October 2025 | 0 | $0.00 | 100.9453 | $322.02 | $322.02 |
| September 2025 | 0 | $0.00 | 158.418 | $470.50 | $470.50 |
SourcesMarket: U.S. Energy Information Administration (Henry Hub for gas, taken per thousand cubic feet). Investors: no public parent's filing is on record for the operator. Tax office and tax approval: Texas Comptroller. The third price shows once the Comptroller's records for this lease have arrived. As of October 1, 2026.
Watch Plus sets these prices beside the price on each of your statements, every month.See Watch Plus
Who takes the oil and gasNew
The gas buyer and the operator share an officer
The State lists who gathers and who buys from each lease. Company filings list who owns whom. Here they are on one drawing.
No shared owner, officer or address on record between the oil buyers and the operator.
Selling to a related company is common and legal. It is also the first thing an auditor looks at, because the price between the two is set inside one company.
Who buys my oilOil price check
SourcesBuyers and gatherers: Railroad Commission Form P-4 records, as of October 24, 2026. Ownership: U.S. Securities and Exchange Commission filings.
Royalty Watch tells you the day the buyer of your oil or gas changes.Watch this lease
Seen from space, 2025New
No satellite heat at this pad in 2025
Weather satellites pass over Texas every night and record heat on the ground. Drag the photo from day to night. Beside it, each night of 2025 next to what the operator reported burning.
A lit dot is a night a satellite recorded heat within 500 m of a well on this lease. The red bar is gas reported vented or flared that month.
nights with heat recorded at this pad, 2025.
months in which flaring was reported.
months with heat seen and no flaring reported.
Where the gas went in 2025, as the operator reported it
SourcesHeat: NOAA-20, NOAA-21 and Suomi NPP (to November 2, 2026) VIIRS active fire product, night readings (NOAA open data); the readings at this pad from NOAA-20, NOAA-21 and Suomi NPP, through November 16, 2026. Reported flaring and gas use: Railroad Commission production reports. Cloud hides heat, so the count of nights is a floor. The satellite records heat. It does not say what burned.
Watch Plus checks whether you were paid on gas in the months heat was seen.See Watch Plus
Where the gas went, month by month
All of the gas went to a transmission line in the last 12 months
Where gas goes decides how it is paid: processed gas can carry plant products and processing fees, gas sold straight to a pipeline usually does not.
SourcesRailroad Commission production reports, gas disposition by code, September 2023 to August 2026.
The county appraisal roll
Roll not on file
County mineral roll
Roll not on file
Nacogdoches Appraisal District’s mineral roll has not been read here yet.
Royalty Clerk has mineral rolls for 159 Texas counties.
Source County appraisal district mineral rolls.
From the state record
What owners ask about Julia Gu
- 01When is the check for August 2026 due?
- Aug 31sale month endsNov 29gas due
- August 2026 is the newest month the state has posted for this lease. Texas law gives the payor until 60 days after the end of the sale month for oil and 90 for gas: the gas by Nov 29, 2026, unless the lease sets another time.
- Source: Railroad Commission production reports; Texas Natural Resources Code §91.402.
- See your next three checks
- 02Which Texas production tax rate applies?
- Gas7.50%
- The Texas Comptroller lists no approved exemption or reduced rate for this lease for August 2026, so the full 7.5% on gas applies.
- Source: Texas Comptroller, approved severance tax exemptions.
- Check the tax on your stub
- 03Who buys the oil and gas?
- CONDPlains Marketing, L.p.100%GASScona LLC100%
- Condensate: Plains Marketing, L.p. gathers it. Gas from gas wells: Scona LLC buys it; Enterprise Products Operating LLC gathers it. The buyer's price is what a royalty check is figured on.
- Source: Railroad Commission Form P-4, gatherers and purchasers.
- See every buyer and past buyers
- 04How many 1099s should an owner expect for 2025?
- 1January to December 2025: one operator of record in all 12 months
- One company, Aethon Energy Operating LLC, filed this lease's reports behind every 2025 check, so most owners get one form. The operator is not always the company that pays, so go by the name on the stubs.
- Source: Railroad Commission production reports, operator of record by month.
- Check your 1099 against it
Every monthly report the State holds
170 months, newest first
| Month | Gas soldthousand cubic feet | Flared or ventedthousand cubic feet | Sold forat public prices | Operator |
|---|---|---|---|---|
| AugustAug 2026 | 10,821 | 0 | $30,100 | Adamas Energy LLC |
| JulyJul 2026 | 10,777 | 0 | $31,100 | Adamas Energy LLC |
| JuneJun 2026 | 10,205 | 0 | $32,100 | Adamas Energy LLC |
| MayMay 2026 | 11,404 | 0 | $33,500 | Adamas Energy LLC |
| AprilApr 2026 | 11,746 | 0 | $32,500 | Adamas Energy LLC |
| MarchMar 2026 | 12,974 | 0 | $39,400 | Adamas Energy LLC |
| FebruaryFeb 2026 | 12,604 | 0 | $45,600 | Aethon Energy Operating LLC |
| JanuaryJan 2026 | 13,837 | 0 | $107,000 | Aethon Energy Operating LLC |
| DecemberDec 2025 | 16,352 | 0 | $69,700 | Aethon Energy Operating LLC |
| NovemberNov 2025 | 34,751 | 0 | $132,000 | Aethon Energy Operating LLC |
| OctoberOct 2025 | 25,842 | 0 | $82,400 | Aethon Energy Operating LLC |
| SeptemberSep 2025 | 40,555 | 0 | $120,000 | Aethon Energy Operating LLC |
| AugustAug 2025 | 21,820 | 0 | $63,500 | Aethon Energy Operating LLC |
| JulyJul 2025 | 24,995 | 0 | $80,000 | Aethon Energy Operating LLC |
| JuneJun 2025 | 24,906 | 0 | $75,200 | Aethon Energy Operating LLC |
| MayMay 2025 | 13,819 | 0 | $43,100 | Aethon Energy Operating LLC |
| AprilApr 2025 | 14,812 | 0 | $50,700 | Aethon Energy Operating LLC |
| MarchMar 2025 | 16,131 | 0 | $66,500 | Aethon Energy Operating LLC |
SourcesTexas Railroad Commission Production Data Query, through August 2026. Prices: EIA.
Likely owed Jan 2025
A whole month was never paid
The state shows 28,175 bbl of oil sold from this lease in January 2025, so your share is 27.51 bbl. No statement covers January 2025. That is the month the operator changed from Endeavor Energy Resources to Diamondback.
Ask Diamondback owner relations: is January 2025 being held in suspense after the change of operator?
$2,277oil + gas
A sample finding, from our example check. The full example found $3,328 likely owed.
Around this lease
Nearby
Adamas Energy LLC in Nacogdoches County
- Michelle Gu296,268 mcf last 12 months
- Blue Jay Gu290,991 mcf last 12 months
- Michelle Gu261,492 mcf last 12 months
- Sun King Gu228,316 mcf last 12 months
- Revolution 9 Gu198,217 mcf last 12 months
- Blue Jay Gu187,776 mcf last 12 months
- Sadie Gu154,900 mcf last 12 months
- Eleanor Rigby Gu143,545 mcf last 12 months
- Penny Lane Gu 1133,939 mcf last 12 months
- Scoggins Gas Unit132,107 mcf last 12 months
Carthage (Haynesville Shale) field
- Fogle Gas Unit216,548 mcf last 12 months
- Richards Gu SBN213,003 mcf last 12 months
- Buford Blow Gu 2-4B211,396 mcf last 12 months
- Denali Gas Unit210,998 mcf last 12 months
- Dunaway-Furrh (Aw)210,573 mcf last 12 months
- S. Timber-Knox Alloc210,021 mcf last 12 months
- Barcoo209,693 mcf last 12 months
- Stego Gas Unit Allocation208,892 mcf last 12 months
- Steele, Corrie Unit208,253 mcf last 12 months
- Grizzlies Du207,725 mcf last 12 months
Leases within 10 km
- Julia Gu438,388 mcf last 12 months · 0.8 km
- Lucy-Julia561,139 mcf last 12 months · 0.8 km
- Lucy-Julia321,148 mcf last 12 months · 0.8 km
- Kendrick, T.j. Gas Unitno production in the last 12 months · 1.1 km
- Greer, Thomas B.349 mcf last 12 months · 1.4 km
- Troy25,265 mcf last 12 months · 1.9 km
- Brown18,189 mcf last 12 months · 1.9 km
- Looking Glass67,462 mcf last 12 months · 2 km
- Kendrick Unit42,376 mcf last 12 months · 2.1 km
- Pace Unit51,465 mcf last 12 months · 2.1 km
Drilling permits within 10 km
- BARTON B #2HBnew drill · horizontal · Apex Natural Gas, LLC · Nov 20, 2026 · 4.1 km
- BARTON A #1Hnew drill · horizontal · Apex Natural Gas, LLC · Nov 20, 2026 · 4.1 km
- BRADLEY HANKS GAS UNIT #1HBnew drill · horizontal · Arenos Energy · Nov 5, 2026 · 5.4 km
- BRADLEY HANKS GAS UNIT #1Hnew drill · horizontal · Arenos Energy · Nov 2, 2026 · 5.4 km
- LUANNE ROSE GAS UNIT #2HBnew drill · horizontal · Arenos Energy · Oct 30, 2026 · 5.4 km
Same name in district 06
- Julia Gu438,388 mcf last 12 months
Where it sits
This county
Where this page comes from
- Railroad Commission of Texas production, Form P-4, permits, wells
- Texas Comptroller tax approvals, lease values
- U.S. Energy Information Administration prices
- SEC EDGAR company filings
- FracFocus frac dates
- NOAA storms and cold
- NOAA-20, NOAA-21 and Suomi NPP (to November 2, 2026) VIIRS active fire product, night readings (NOAA open data) night heat
- U.S. Geological Survey photos