Skip to content
Royalty Clerk

Texas oil lease

Producing

MISS KITTY A 669-704

Miss Kitty A 669-704 is an oil lease in Yoakum County, Texas, operated by Riley Permian Operating Co, LLC in the Platang (San Andres) field.

2 wells

71,852bbl oil, last 12 months−1% vs prior year
RRC lease
8A-70962

Is your check right?

Check my statement

Where it sits

This county

Yoakum CountyYoakumHockleyCochranTerryYoakum County
Yoakum County
Gas, last 12 months
243,510 mcf
Oil in Jul 2026
5,902 bbl

Checks stopped on this lease?

  • Buyer

    Buyer changed: TARGA SAN ANDRES GAS SERVICES LL replaced STAKEHOLDER GAS SERVICES, LLC as the buyer of this lease's gas from oil wells on Jan 6, 2026.

SourceRailroad Commission production, P-5 and P-4 records, data through Jul 2026.

See why checks stop on this lease

Production by month

Oil output held steady over the last 12 months

  • Oil (bars)
  • Gas (line)
  • Last 12 months
Oil output held steady over the last 12 monthsMonthly oil production and gas for MISS KITTY A 669-704, Aug 2023 to Jul 2026. Oil output held steady over the last 12 months. 71,852 bbl in the 12 months through Jul 2026, against 72,940 bbl in the 12 months before.Last 12 months: 71,852 bblbbl per monthmcf per month002,50010k5,00020k7,50030k10k40kOct 23Jan 24AprJulOctJan 25AprJulOctJan 26AprJul
Oil output held steady over the last 12 monthsMonthly oil production and gas for MISS KITTY A 669-704, Aug 2023 to Jul 2026. Oil output held steady over the last 12 months. 71,852 bbl in the 12 months through Jul 2026, against 72,940 bbl in the 12 months before.Last 12 monthsbbl per monthmcf per month002,50010k5,00020k7,50030k10k40kJan 24JulJan 25JulJan 26Jul

SourceTexas Railroad Commission Production Data Query, through Jul 2026.

Where the gas went

Since Jul 2024 the lease's gas goes to a transmission line instead of a processing plant

Flaring peaked at 71.3% of the gas in Sep 2023.

  • Processing plant (3)
  • Transmission line (2)
  • Flared (4)
Since Jul 2024 the lease's gas goes to a transmission line instead of a processing plantShare of MISS KITTY A 669-704 gas by disposition code each month, Aug 2023 to Jul 2026. Since Jul 2024 the lease's gas goes to a transmission line instead of a processing plant. Flaring peaked at 71.3% of the gas in Sep 2023.Share of the lease’s gas by disposition code, per month0%50%100%Jul 2024: plant to lineFlared 71.3%Oct 23Jan 24AprJulOctJan 25AprJulOctJan 26AprJul
Since Jul 2024 the lease's gas goes to a transmission line instead of a processing plantShare of MISS KITTY A 669-704 gas by disposition code each month, Aug 2023 to Jul 2026. Since Jul 2024 the lease's gas goes to a transmission line instead of a processing plant. Flaring peaked at 71.3% of the gas in Sep 2023.Share of gas by disposition code0%50%100%Jul 24: plant to lineFlared 71.3%Jan 24JulJan 25JulJan 26Jul

SourceTexas Railroad Commission Production Data Query, through Jul 2026.

  • Transmission line (2)

    98% · 238,743 mcf

  • Flared (4)

    2.0% · 4,767 mcf

2.0% of the gas flared in the last 12 months. 22 months above 3%.

2 wells on this lease

Wells on MISS KITTY A 669-704
API numberWell no.Status
42-501-3712725XHActive
42-501-372874XHActive

SourceTexas Railroad Commission Wellbore Query.

Buyers and gatherers

Companies named on the Form P-4, by product
CompanyProductRoleShare%FromUntil
Targa San Andres Crude PipelineOilGathers100Jan 6, 2026–
Targa San Andres Gas Services LlCasinghead gasBuys100Jan 6, 2026–
Targa San Andres Gas Utility LLCCasinghead gasGathers100Jan 6, 2026–
Stakeholder Gas Utility, LLCCasinghead gasGathers100Jul 18, 2019Jan 6, 2026
Stakeholder Gas Services, LLCCasinghead gasBuys100Jul 18, 2019Jan 6, 2026
Stakeholder Ms Crude Oil Pl LLCOilGathers100Jul 18, 2019Jan 6, 2026

SourceRailroad Commission Form P-4 file, Sep 24, 2026 (source).

544 acres on the newest permit

  • Good to know

    The wells on this lease state different acreage

    The permits state between 480.38 and 544 acres. Use the acres from your own division order for the well you are paid on.

  • Worth asking

    A Rule 37 case is listed

    The RRC permit records list a Rule 37 case. This does not establish your royalty share. Ask for the permit and unit plat for your well.

Check your decimal on this lease
Permits for Miss Kitty A 669-704
API numberWell no.Acreson the permit
42-501-372874XH544
42-501-3712725XH480.38

SourceRailroad Commission drilling permits, Oct 3, 2026 (source 1, source 2).

Estimate your royalty

36 months, newest first

Ledger for MISS KITTY A 669-704
MonthOil producedbblOil soldbblGas producedmcfGas soldmcf, codes 2+3FlaredmcfWTI$/bblHenry Hub$/MMBtu
Jul 20265,9025,85018,52317,710813$80.46$2.89
Jun 20265,6925,74519,25519,144111$84.81$3.15
May 20266,0015,96220,34119,575766$102.13$2.94
Apr 20265,8735,89320,39318,2952,098$100.32$2.77
Mar 20266,4636,46820,87220,342530$91.38$3.04
Feb 20265,6135,60617,92617,9260$64.51$3.62
Jan 20265,9386,13720,70420,67727$60.04$7.72
Dec 20256,1736,04521,30821,3071$57.97$4.26
Nov 20255,8915,90321,03721,0325$60.06$3.79
Oct 20256,0696,09521,50321,5030$60.89$3.19
Sep 20255,9756,00220,87620,8733$63.96$2.97
Aug 20256,2626,31220,77220,359413$64.86$2.91
Jul 20255,9705,73520,58020,461119$68.39$3.20
Jun 20255,5615,67917,67815,1832,495$68.17$3.02
May 20256,0106,01219,50717,2602,247$62.17$3.12
Apr 20255,5285,49319,42517,7541,671$63.54$3.42
Mar 20256,2166,24317,25814,3302,928$68.24$4.12
Feb 20255,3125,38914,23013,2191,011$71.53$4.19
Jan 20255,7725,72315,93015,732198$75.74$4.13
Dec 20245,8385,81215,58115,392189$70.12$3.01
Nov 20245,5675,58013,16513,060105$69.95$2.12
Oct 20246,5586,54715,11214,522590$71.99$2.20
Sep 20247,2707,33122,33419,5262,808$70.24$2.28
Aug 20247,3387,31925,12524,425700$76.68$1.99
Jul 20247,3927,41326,50224,8351,667$81.80$2.07
Jun 20246,4646,44419,45410,5818,873$79.77$2.54
May 20246,0966,18219,83815,7084,130$80.02$2.12
Apr 20247,1207,04120,79514,6946,101$85.35$1.60
Mar 20247,5987,58522,62316,2996,324$81.28$1.49
Feb 20247,0146,98419,42513,7185,707$77.25$1.72
Jan 20246,6956,62718,72810,3928,336$74.15$3.18
Dec 20236,4456,40920,80115,6045,197$71.90$2.52
Nov 20236,6176,71219,51014,5284,982$77.69$2.71
Oct 20238,9758,93325,34317,3677,976$85.64$2.98
Sep 20237,2267,28521,4156,15315,262$89.43$2.64
Aug 20238,8748,94125,88011,94313,937$81.39$2.58

Flared above 3%

SourceTexas Railroad Commission Production Data Query, through Jul 2026. Prices: EIA, through Aug 2026. Updated Oct 2, 2026.

How to check your stub against this lease Checks stopped on this lease? See the likely reasons

Do your checks match this lease?

Nearby

Leases within 10 km

Drilling permits within 10 km