Texas gas wellRRC 09-187818
Harrison
One well on 320 acres in Denton County. The lease produced 17,523 thousand cubic feet of gas in its last 12 months on record, through July 2026. No report after July 2026 is on file; the State's newest month is August 2026.
- Operator
- Lime Rock Resources IV-A, L.P.
- County
- Denton
- On record since
- December 2001
- Newest report on file
- July 2026
- Unit on the newest permit
- 320 acres
Outline: the original land surveys this lease's wells sit in. The State publishes no lease outlines. RRC surveys, 2026-09-29.
The story, from 296 monthly reports
On record since December 2001
December 2001: the first month the lease sold gas on record, 10,678 thousand cubic feet.
September 2002: Burlington Resources O & G Co LP took over from Dallas Production, Inc..
November 2018: Lime Rock Resources IV-A, L.P. took over from Burlington Resources O & G Co LP.
July 2022 to August 2022: two months in a row with no oil and no gas reported.
July 2026 is the newest monthly production report on file.
SourceRailroad Commission production reports, December 2001 through August 2026. Not a forecast, not reserves.
297 months against 7 other recordsNew
Every month since December 2001, and what else happened that month
The lease is the line on top. Under it, on the same clock: the weather, the State, the price, the wells next door, who ran the lease, who bought from it and the rest of the field. Move across it.
Gas averaged $2.99 an mcf · Burlington Resources O & G Co LP
- Nothing else on record this month.
Move the pointer or drag across the chart. The numbered buttons jump to each drop.
Monthly gas sold from this lease since December 2001, with eight record tracks beneath it. Use the left and right arrow keys to move month by month.. 297 months from December 2001 to August 2026. The most in one month: 23,240 mcf, January 2002. The newest month: 0 mcf. 9 months with nothing reported. Moments marked: 1, Nov 2005; 2, Dec 2005; 3, Jan 2006; 4, Oct 2008; 5, Nov 2008; 6, May 2010; 7, Jun 2010; 8, Jun 2015.
SourcesProduction, cut-offs, operators and buyers: Railroad Commission of Texas. Weather: NOAA. Prices: U.S. Energy Information Administration. Fracs: FracFocus. A record in the same month is not proof of a cause. Through August 2026. The newest report on file for this lease is for July 2026; no report after it is on file.
Royalty Watch tells you the month a drop starts, with the records from that month.Watch this lease
294 months, one line eachNew
Two months of silence in 2022
A gap is a month with no oil and no gas reported. Many leases end after 60 to 90 days without production unless the lease says otherwise.
months in a row with nothing reported, July to August 2022. Reports are on file for all 2 months, with no oil and no gas. The only silence on record here.
thousand cubic feet of gas on the newest report on file with oil or gas, for July 2026. No report after July 2026 is on file; the State's newest month is August 2026.
of 294 months with oil or gas reported since December 2001.
thousand cubic feet of gas a day on average from September 2025 through August 2026, counting a month with no report on file as zero.
A shut-in payment or work on the wells can keep a lease alive through a gap. Your own lease paper decides.
SourceRailroad Commission production reports, December 2001 through May 2026. The newest months, after May 2026, are left out of the count because reports arrive late.
Royalty Watch tells you when a silent month starts, and drafts the letter asking whether the lease is still in force.Watch this lease
26 years of state records, 2001 to 2026
Sold since December 2001
$4.47million
Only filed sales with a published price are included. Some sales figures or prices are unavailable.
- Oil sold
- 7,814barrels
- Gas sold
- 898,260thousand cubic feet
| Year | Oil, dollars | Gas, dollars | Total |
|---|---|---|---|
| 2001 | $0 | $24,600 | $24,600 |
| 2002 | $78,500 | $503,000 | $581,000 |
| 2003 | $45,500 | $545,000 | $590,000 |
| 2004 | $36,100 | $428,000 | $464,000 |
| 2005 | $32,900 | $503,000 | $536,000 |
| 2006 | $15,400 | $150,000 | $166,000 |
| 2007 | $12,600 | $286,000 | $298,000 |
| 2008 | $22,200 | $319,000 | $341,000 |
| 2009 | $4,840 | $81,400 | $86,200 |
| 2010 | $9,150 | $124,000 | $133,000 |
| 2011 | $12,300 | $150,000 | $163,000 |
| 2012 | $14,100 | $90,500 | $105,000 |
| 2013 | $6,070 | $122,000 | $128,000 |
| 2014 | $14,900 | $129,000 | $144,000 |
| 2015 | $0 | $33,600 in priced filings | $33,600 in priced filings |
| 2016 | $5,280 | $62,300 | $67,500 |
| 2017 | $0 | $75,600 | $75,600 |
| 2018 | $0 | $74,600 | $74,600 |
| 2019 | $6,390 | $51,100 | $57,500 |
| 2020 | $41 | $32,400 | $32,500 |
| 2021 | $2,860 | $68,500 | $71,300 |
| 2022 | $6,990 | $94,000 | $101,000 |
| 2023 | $298 | $53,600 | $53,900 |
| 2024 | $4,680 | $36,100 | $40,800 |
| 2025 | $0 | $62,200 | $62,200 |
| 2026, 2026 so far | $0 | $38,300 | $38,300 |
Did a relative own a share of this lease?
SourcesRailroad Commission Production Data Query, every monthly report since December 2001. EIA monthly WTI and Henry Hub prices. 2026 is part of a year, drawn lighter. Not a forecast, not reserves.
Who has run this lease
The operator changed two times, most recently in November 2018
The company named on each monthly report to the State. The operator is not always the company that pays.
- Lime Rock Resources IV-A, L.P.November 2018 to now
- Burlington Resources O & G Co LPSeptember 2002 to October 2018
- Dallas Production, Inc.December 2001 to August 2002
SourcesRailroad Commission production reports, the operator on each month’s report, December 2001 through August 2026.
The newest well, seen from the side
No well on the way. Well 2 was completed in December 2001.
- Permit filedNot on file
- Drilling startedNot on file
- FrackedNot on file
- Completion filedDecember 19, 2001
- First production on the leaseNot on file
- First checkNot on file
SourcesRailroad Commission drilling permits and well records, and the FracFocus registry. Lease record built November 17, 2026.
Royalty Watch follows new well permits and completions on this lease.Watch this lease
About 6 miles across
Wells on this lease and around it
For a lawyer, a buyer or a probate file. Wells and permits within about 2 miles. Railroad Commission of Texas, FracFocus and USGS imagery.
From the State's well records
One well on this lease
| Well | API number | Completed | Depthfeet | Today |
|---|---|---|---|---|
| 2 | 42-121-31259 | December 2001 | 8,751 | Active |
SourceRailroad Commission wellbore and completion records.
What the drilling permits say
320acres on the newest permit
- 320 acres, on the 2001 permits
Gas, August 2026, dollars per thousand cubic feet New
Four prices for the same gas
What the market paid, what the operator told its investors, what it told the tax office for this lease, and the one only you hold.
The State approved a lower tax for this lease
- Kind
- Low Producing Wells
- Wells
- The whole lease
- Runs
- May 2009 to no end date on file
- Rate
- Not given in the file
Look at the tax line on your statement for this lease. The record says which rate applies.
Estimate your royalty
Type the decimal from your division order
The starting decimal is an example. Nothing you type here leaves this page.
$21a month
At these prices the whole lease’s reported sales were about $63,200 over 12 reported months. Your estimated share is $247 before taxes and deductions.
Monthly owner volumes and values
| Month | Oil (bbl) | Oil value | Gas (mcf) | Gas value | Total |
|---|---|---|---|---|---|
| July 2026 | 0 | $0.00 | 5.8359 | $16.87 | $16.87 |
| June 2026 | 0 | $0.00 | 5.6875 | $17.92 | $17.92 |
| May 2026 | 0 | $0.00 | 5.8672 | $17.25 | $17.25 |
| April 2026 | 0 | $0.00 | 5.7227 | $15.85 | $15.85 |
| March 2026 | 0 | $0.00 | 5.9102 | $17.97 | $17.97 |
| February 2026 | 0 | $0.00 | 5.3203 | $19.26 | $19.26 |
| January 2026 | 0 | $0.00 | 5.7695 | $44.54 | $44.54 |
| December 2025 | 0 | $0.00 | 5.8906 | $25.09 | $25.09 |
| November 2025 | 0 | $0.00 | 5.7461 | $21.78 | $21.78 |
| October 2025 | 0 | $0.00 | 4.9961 | $15.94 | $15.94 |
| September 2025 | 0 | $0.00 | 5.6875 | $16.89 | $16.89 |
| August 2025 | 0 | $0.00 | 6.0156 | $17.51 | $17.51 |
SourcesMarket: U.S. Energy Information Administration (Henry Hub for gas, taken per thousand cubic feet). Investors: no public parent's filing is on record for the operator. Tax office and tax approval: Texas Comptroller. The third price shows once the Comptroller's records for this lease have arrived. As of October 1, 2026.
Watch Plus sets these prices beside the price on each of your statements, every month.See Watch Plus
Who takes the oil and gasNew
No buyer shares an owner with the operator
The State lists who gathers and who buys from each lease. Company filings list who owns whom. Here they are on one drawing.
No shared owner, officer or address on record between the gas buyers and the operator.
No shared owner, officer or address on record between the oil buyers and the operator.
Earlier buyers and gatherers, back to 1993
| Company | Product | Role | From | Until |
|---|---|---|---|---|
| GULFMARK ENERGY, INC. | Oil | Gathers | Nov 2018 | Nov 2023 |
| CONOCOPHILLIPS COMPANY | Gas | Buys | Mar 2009 | Nov 2019 |
Who buys my oilOil price check
SourcesBuyers and gatherers: Railroad Commission Form P-4 records, as of October 24, 2026. Ownership: U.S. Securities and Exchange Commission filings.
Royalty Watch tells you the day the buyer of your oil or gas changes.Watch this lease
Seen from space, 2025New
No satellite heat at this pad in 2025
Weather satellites pass over Texas every night and record heat on the ground. Drag the photo from day to night. Beside it, each night of 2025 next to what the operator reported burning.
A lit dot is a night a satellite recorded heat within 500 m of a well on this lease. The red bar is gas reported vented or flared that month.
nights with heat recorded at this pad, 2025.
months in which flaring was reported.
months with heat seen and no flaring reported.
Where the gas went in 2025, as the operator reported it
SourcesHeat: NOAA-20, NOAA-21 and Suomi NPP (to November 2, 2026) VIIRS active fire product, night readings (NOAA open data); the readings at this pad from NOAA-20, NOAA-21 and Suomi NPP, through November 16, 2026. Reported flaring and gas use: Railroad Commission production reports. Cloud hides heat, so the count of nights is a floor. The satellite records heat. It does not say what burned.
Watch Plus checks whether you were paid on gas in the months heat was seen.See Watch Plus
Where the gas went, month by month
All of the gas went to a transmission line in the last 12 months
Where gas goes decides how it is paid: processed gas can carry plant products and processing fees, gas sold straight to a pipeline usually does not.
SourcesRailroad Commission production reports, gas disposition by code, September 2023 to July 2026.
The county appraisal roll
No public roll figures
County mineral roll
No public roll figures
There are no publishable figures for this lease from the 2026 county mineral roll.
Royalty Clerk has mineral rolls for 163 Texas counties.
Source County appraisal district mineral rolls.
From the state record
What owners ask about Harrison
- 01When is the check for July 2026 due?
- Jul 31sale month endsOct 29gas due
- July 2026 is the newest month the state has posted for this lease. Texas law gives the payor until 60 days after the end of the sale month for oil and 90 for gas: the gas by Oct 29, 2026, unless the lease sets another time.
- Source: Railroad Commission production reports; Texas Natural Resources Code §91.402.
- See your next three checks
- 02Which Texas production tax rate applies?
- Gas7.50%
- The Texas Comptroller lists low producing wells for this lease, from May 1, 2009. Its file does not give the rate, so we compare your stub with the full 7.5%. That is for July 2026.
- Source: Texas Comptroller, approved severance tax exemptions.
- Check the tax on your stub
- 03Who buys the oil and gas?
- CONDPtt Premier Trading and Tran LLC100%GASLime Rock Resources Iv-A, L.p.100%
- Condensate: Ptt Premier Trading and Tran LLC gathers it. Gas from gas wells: Lime Rock Resources Iv-A, L.p. buys it; Targa Midstream Services LLC gathers it. The buyer's price is what a royalty check is figured on.
- Source: Railroad Commission Form P-4, gatherers and purchasers.
- See every buyer and past buyers
- 04How many 1099s should an owner expect for 2025?
- 1January to December 2025: one operator of record in all 12 months
- One company, Lime Rock Resources IV-A, L.P., filed this lease's reports behind every 2025 check, so most owners get one form. The operator is not always the company that pays, so go by the name on the stubs.
- Source: Railroad Commission production reports, operator of record by month.
- Check your 1099 against it
Every monthly report the State holds
297 months, newest first
| Month | Oil soldbarrels | Gas soldthousand cubic feet | Flared or ventedthousand cubic feet | Sold forat public prices | Operator |
|---|---|---|---|---|---|
| AugustAug 2026 | No report on file | – | |||
| JulyJul 2026 | 0 | 1,494 | 0 | $4,320 | Lime Rock Resources IV-A, L.P. |
| JuneJun 2026 | 0 | 1,456 | 0 | $4,590 | Lime Rock Resources IV-A, L.P. |
| MayMay 2026 | 0 | 1,502 | 0 | $4,420 | Lime Rock Resources IV-A, L.P. |
| AprilApr 2026 | 0 | 1,465 | 0 | $4,060 | Lime Rock Resources IV-A, L.P. |
| MarchMar 2026 | 0 | 1,513 | 0 | $4,600 | Lime Rock Resources IV-A, L.P. |
| FebruaryFeb 2026 | 0 | 1,362 | 0 | $4,930 | Lime Rock Resources IV-A, L.P. |
| JanuaryJan 2026 | 0 | 1,477 | 0 | $11,400 | Lime Rock Resources IV-A, L.P. |
| DecemberDec 2025 | 0 | 1,508 | 0 | $6,420 | Lime Rock Resources IV-A, L.P. |
| NovemberNov 2025 | 0 | 1,471 | 0 | $5,580 | Lime Rock Resources IV-A, L.P. |
| OctoberOct 2025 | 0 | 1,279 | 0 | $4,080 | Lime Rock Resources IV-A, L.P. |
| SeptemberSep 2025 | 0 | 1,456 | 0 | $4,320 | Lime Rock Resources IV-A, L.P. |
| AugustAug 2025 | 0 | 1,540 | 0 | $4,480 | Lime Rock Resources IV-A, L.P. |
| JulyJul 2025 | 0 | 1,527 | 0 | $4,890 | Lime Rock Resources IV-A, L.P. |
| JuneJun 2025 | 0 | 1,393 | 0 | $4,210 | Lime Rock Resources IV-A, L.P. |
| MayMay 2025 | 0 | 1,414 | 0 | $4,410 | Lime Rock Resources IV-A, L.P. |
| AprilApr 2025 | 0 | 1,411 | 0 | $4,830 | Lime Rock Resources IV-A, L.P. |
| MarchMar 2025 | 0 | 1,462 | 0 | $6,020 | Lime Rock Resources IV-A, L.P. |
SourcesTexas Railroad Commission Production Data Query, through August 2026. Prices: EIA.
Likely owed Jan 2025
A whole month was never paid
The state shows 28,175 bbl of oil sold from this lease in January 2025, so your share is 27.51 bbl. No statement covers January 2025. That is the month the operator changed from Endeavor Energy Resources to Diamondback.
Ask Diamondback owner relations: is January 2025 being held in suspense after the change of operator?
$2,277oil + gas
A sample finding, from our example check. The full example found $3,328 likely owed.
Around this lease
Nearby
Lime Rock Resources IV-A, L.P. in Denton County
- Shifflett "A"17,664 mcf last 12 months
- Burel Unit16,384 mcf last 12 months
- Parkey B15,680 mcf last 12 months
- Burkhalter, Ewell15,351 mcf last 12 months
- Langley "A" Unit15,887 mcf last 12 months
- Langley "A" Unit15,663 mcf last 12 months
- Fairman B Unit14,944 mcf last 12 months
- Banks "A"15,258 mcf last 12 months
- Caddell Unit14,318 mcf last 12 months
- Huey, Griffin14,986 mcf last 12 months
Newark, East (Barnett Shale) field
- Hardeman, C. J.17,539 mcf last 12 months
- Sansone-Robertson (Sa) "A"17,533 mcf last 12 months
- West & West17,529 mcf last 12 months
- Dcco 417,520 mcf last 12 months
- Tolbert17,520 mcf last 12 months
- Mitchell Ranch17,516 mcf last 12 months
- McCurdy, Floyd "A"17,511 mcf last 12 months
- Sewell Ranch, Inc.17,503 mcf last 12 months
- Esther Beeson (Aw)16,849 mcf last 12 months
- Bryan "D"17,493 mcf last 12 months
Leases within 10 km
- Harrison Unit2 mcf last 12 months · 0.1 km
- Shifflett "A"17,664 mcf last 12 months · 0.3 km
- Harrison Unit48,101 mcf last 12 months · 0.3 km
- Harrison Unit7,718 mcf last 12 months · 0.4 km
- Boyd19,122 mcf last 12 months · 0.4 km
- Shifflett "A"8,392 mcf last 12 months · 0.4 km
- Shifflett "A"6,405 mcf last 12 months · 0.5 km
- Boyd15,792 mcf last 12 months · 0.5 km
- Boyd17,327 mcf last 12 months · 0.6 km
- Boydno production in the last 12 months · 0.7 km
Drilling permits within 10 km
- SCHWARZ, DIETER GU 'A' 16 (AW) #16Hrecompletion · horizontal · BKV Barnett, LLC · Nov 16, 2026 · 8 km
- MASON, ROSE 4 (AW) #4Hnew drill · horizontal · BKV Barnett, LLC · Sept 24, 2026 · 6.7 km
- MASON, ROSE 6 (AW) #6Hnew drill · horizontal · BKV Barnett, LLC · Sept 24, 2026 · 6.7 km
- MASON, ROSE 5 (AW) #5Hnew drill · horizontal · BKV Barnett, LLC · Sept 11, 2026 · 6.7 km
- MASON, ROSE 3 (AW) #3Hnew drill · horizontal · BKV Barnett, LLC · Sept 11, 2026 · 6.7 km
Same name in district 09
Sister leases
- Harrison Unit76,527 mcf last 12 months
- Harrison Unit66,983 mcf last 12 months
- Harrison Unit67,586 mcf last 12 months
- Harrison Unit48,101 mcf last 12 months
- Harrison Unit7,718 mcf last 12 months
- Harrison Unitno production in the last 12 months
- Harrison Unitno production in the last 12 months
- Harrison Unitno production in the last 12 months
Where it sits
This county
Where this page comes from
- Railroad Commission of Texas production, Form P-4, permits, wells
- Texas Comptroller tax approvals, lease values
- U.S. Energy Information Administration prices
- FracFocus frac dates
- NOAA storms and cold
- NOAA-20, NOAA-21 and Suomi NPP (to November 2, 2026) VIIRS active fire product, night readings (NOAA open data) night heat
- U.S. Geological Survey photos