Texas oil leaseRRC 01-16120Producing
Jea Unit V Las
One well in La Salle County. The lease produced 1,784 barrels of oil in the last 12 months, through September 2026.
- Operator
- Ineos USA Oil & Gas LLC
- County
- La Salle
- On record since
- October 2023
- Newest report on file
- September 2026
- Wells
- 1
What the checks found on this lease
- 27 silent months. Oil or gas produced in 9 of 36 months since October 2023. Of the 27 other months, 27 with a report on file showing no oil and no gas.
Not on file here, or only in part: drops, buyers, price and tax, heat from space and new wells.
Royalty Watch tells you the month any of this changes on your own lease: a silent month, a drop, a new buyer or a well's next stage.Watch this lease
The story, from 36 monthly reports
2023 to 2026: it sold the most in 2023
October 2023: the first month the lease sold oil on record, 709 barrels.
September 2026 is the newest monthly production report on file.
SourceRailroad Commission production reports, October 2023 through September 2026. Not a forecast, not reserves.
36 months against 7 other recordsNew
Every month since October 2023, and what else happened that month
The lease is the line on top. Under it, on the same clock: the weather, the State, the price, the wells next door, who ran the lease, who bought from it and the rest of the field. Move across it.
Oil averaged $97.31 a barrel · Ineos USA Oil & Gas LLC
- Nothing else on record this month.
Move the pointer or drag across the chart.
Monthly oil sold from this lease since October 2023, with eight record tracks beneath it. Use the left and right arrow keys to move month by month.. 36 months from October 2023 to September 2026. The most in one month: 1,368 barrels, September 2026. The newest month: 1,368 barrels. 28 months with nothing reported.
No numbered drop comparison is on file here.
Some comparison records were unavailable when this page was read.
SourcesProduction, cut-offs, operators and buyers: Railroad Commission of Texas. Weather: NOAA. Prices: U.S. Energy Information Administration. Fracs: FracFocus. A record in the same month is not proof of a cause. Through September 2026.
One line per month
27 months with a report showing no oil and no gas
months with a report on file showing no oil and no gas.
months with oil or gas produced.
months in view.
SourcesRailroad Commission production reports, through September 2026.
15 years of state records, 2012 to 2026
Sold since July 2012
$17.2million
Only filed sales with a published price are included. Some sales figures or prices are unavailable.
- Oil sold
- 206,427barrels
- Gas sold
- 331,563thousand cubic feet
| Year | Oil, dollars | Gas, dollars | Total |
|---|---|---|---|
| 2012 | $1.78 million | $33,500 in priced filings | $1.81 million in priced filings |
| 2013 | $5.74 million | $246,000 in priced filings | $5.99 million in priced filings |
| 2014 | $3.57 million | $353,000 | $3.93 million |
| 2015 | $986,000 | $112,000 | $1.1 million |
| 2016 | $669,000 | $82,000 | $751,000 |
| 2017 | $509,000 | $70,000 | $579,000 |
| 2018 | $502,000 | $59,400 | $561,000 |
| 2019 | $507,000 | $50,100 | $557,000 |
| 2020 | $286,000 | $25,400 | $312,000 |
| 2021 | $409,000 | $54,800 | $464,000 |
| 2022 | $461,000 | $1,970 | $463,000 |
| 2023 | $393,000 | $18,700 | $412,000 |
| 2024 | $89,100 | $3,530 | $92,700 |
| 2025 | $0 | $0 | $0 |
| 2026, 2026 so far | $167,000 | $4,400 | $172,000 |
Did a relative own a share of this lease?
SourcesRailroad Commission Production Data Query, every monthly report since July 2012. EIA monthly WTI and Henry Hub prices. 2026 is part of a year, drawn lighter. Not a forecast, not reserves.
Who has run this lease
The operator changed once, most recently in September 2023
The company named on each monthly report to the State. The operator is not always the company that pays.
- Ineos USA Oil & Gas LLCSeptember 2023 to now
- Chesapeake Operating, L.L.C.January 2020 to August 2023
A new operator sets up every owner again before it pays, and often sends a new division order. See what you may sign
SourcesRailroad Commission production reports, the operator on each month’s report, January 2020 through September 2026.
The newest well, seen from the side
Current well stages unavailable. Well J 1H was completed in June 2012.
- Permit filedNot on file
- Drilling startedNot on file
- FrackedNot on file
- Completion filedJune 14, 2012
- First production on the leaseNot on file
- First checkNot on file
SourcesRailroad Commission drilling permits and well records, and the FracFocus registry. Source date unavailable.
Wells on this lease and around it
The nearby well map is unavailable. The locator shows La Salle County.
From the State's well records
One well on this lease
| Well | API number | Completed | Depthfeet | Today |
|---|---|---|---|---|
| J 1H | 42-283-33033 | June 2012 | 8,916 | Shut in |
SourceRailroad Commission wellbore and completion records.
Oil · last sale month, September 2026 New
Four prices for the same oil
Last sale September 2026. WTI $97.31 in September 2026, the last sale month.
Texas Comptroller
Lower tax on record?
The tax approval record is unavailable for this lease.
Estimate your royalty
Type the decimal from your division order
The starting decimal is an example. Nothing you type here leaves this page.
$56a month
At these prices the whole lease’s reported sales were about $172,000 over 12 reported months. Your estimated share is $671 before taxes and deductions.
Monthly owner volumes and values
| Month | Oil (bbl) | Oil value | Gas (mcf) | Gas value | Total |
|---|---|---|---|---|---|
| September 2026 | 5.3438 | $520.00 | 5.4375 | $16.04 | $536.04 |
| August 2026 | 1.5977 | $134.04 | 0.4141 | $1.15 | $135.19 |
| July 2026 | 0 | $0.00 | 0 | $0.00 | $0.00 |
| June 2026 | 0 | $0.00 | 0 | $0.00 | $0.00 |
| May 2026 | 0 | $0.00 | 0 | $0.00 | $0.00 |
| April 2026 | 0 | $0.00 | 0 | $0.00 | $0.00 |
| March 2026 | 0 | $0.00 | 0 | $0.00 | $0.00 |
| February 2026 | 0 | $0.00 | 0 | $0.00 | $0.00 |
| January 2026 | 0 | $0.00 | 0 | $0.00 | $0.00 |
| December 2025 | 0 | $0.00 | 0 | $0.00 | $0.00 |
| November 2025 | 0 | $0.00 | 0 | $0.00 | $0.00 |
| October 2025 | 0 | $0.00 | 0 | $0.00 | $0.00 |
SourcesRailroad Commission monthly production, EIA WTI, SEC filings and Texas Comptroller records.
Watch Plus sets public prices beside the price on your statement.See Watch Plus
The State’s Form P-4
Who takes the oil and gas
The Form P-4 purchaser records could not be confirmed. A shared owner cannot be checked without the other party.
SourcesRailroad Commission Form P-4.
Seen from space
Heat at the pad, beside reported gas use
Satellite match
Satellite record unavailable
Satellite coverage for this pad could not be confirmed.
nights of heat
months reporting flared or vented gas among 12 filed months, October 2025 to September 2026
months with heat and none reported
SourcesNOAA VIIRS night readings and Railroad Commission gas disposition reports.
Watch Plus checks statement months beside the satellite record.See Watch Plus
Where the gas went, month by month
90% of the gas went to a transmission line in the 9 months reported
Where gas goes decides how it is paid: processed gas can carry plant products and processing fees, gas sold straight to a pipeline usually does not.
- Transmission line (2)90% · 4,738 mcf
- Lease fuel (1)10% · 534 mcf
SourcesRailroad Commission production reports, gas disposition by code, October 2023 to September 2026.
The county appraisal roll
Roll match unavailable
County mineral roll
Roll match unavailable
The county roll could not be confirmed for this lease.
Source County appraisal district mineral rolls.
From the state record
What owners ask about Jea Unit V Las
- 01When is the check for September 2026 due?
- Sept 30sale month endsNov 29oil dueDec 29gas due
- September 2026 is the newest month the state has posted for this lease. Texas law gives the payor until 60 days after the end of the sale month for oil and 90 for gas: the oil by Nov 29, 2026 and the gas by Dec 29, 2026, unless the lease sets another time.
- Source: Railroad Commission production reports; Texas Natural Resources Code §91.402.
- See your next three checks
- 02How many 1099s should an owner expect for 2025?
- 1January to December 2025: one operator of record in all 12 months
- One company, Ineos USA Oil & Gas LLC, filed this lease's reports behind every 2025 check, so most owners get one form. The operator is not always the company that pays, so go by the name on the stubs.
- Source: Railroad Commission production reports, operator of record by month.
- Check your 1099 against it
Every monthly report the State holds
36 months, newest first
| Month | Oil soldbarrels | Gas soldthousand cubic feet | Flared or ventedthousand cubic feet | Sold forat public prices |
|---|---|---|---|---|
| SeptemberSep 2026 | 1,368 | 1,392 | 0 | $137,000 |
| AugustAug 2026 | 409 | 106 | 0 | $34,600 |
| JulyJul 2026 | No oil or gas reported | |||
| JuneJun 2026 | No oil or gas reported | |||
| MayMay 2026 | No oil or gas reported | |||
| AprilApr 2026 | No oil or gas reported | |||
| MarchMar 2026 | No oil or gas reported | |||
| FebruaryFeb 2026 | No oil or gas reported | |||
| JanuaryJan 2026 | No oil or gas reported | |||
| DecemberDec 2025 | No oil or gas reported | |||
| NovemberNov 2025 | No oil or gas reported | |||
| OctoberOct 2025 | No oil or gas reported | |||
| SeptemberSep 2025 | No oil or gas reported | |||
| AugustAug 2025 | No oil or gas reported | |||
| JulyJul 2025 | No oil or gas reported | |||
| JuneJun 2025 | No oil or gas reported | |||
| MayMay 2025 | No oil or gas reported | |||
| AprilApr 2025 | No oil or gas reported | |||
SourcesTexas Railroad Commission Production Data Query, through September 2026. Prices: EIA.
Example
A whole month was never paid
The State shows 28,175 barrels of oil sold from the lease in the month its operator changed from Operator A to Operator B, so the owner's share is 27.51 barrels. No statement covers that month.
Ask Operator B's owner relations: is that month held in suspense after the change of operator?
$2,277oil and gas
A sample finding, from our example check.
Around this lease
Nearby
Ineos USA Oil & Gas LLC in La Salle County
- 7K Unit V Las1,687 bbl last 12 months
- Foster Las40,766 mcf last 12 months
- Fiedler Unit Las1,655 bbl last 12 months
- Thurman16,028 mcf last 12 months
- Foster Las44,004 mcf last 12 months
- Foster Las40,316 mcf last 12 months
- Wolf B16,415 mcf last 12 months
- Kersh Unit I Las1,784 bbl last 12 months
- Thurman9,573 mcf last 12 months
- Kersh Unit III Las1,611 bbl last 12 months
Eagleville (Eagle Ford-1) field
- Tyler Unit H1,567 bbl last 12 months
- Steen Scruggs Unit4,871 mcf last 12 months
- Foster Las40,316 mcf last 12 months
- Eland Unit1,852 bbl last 12 months
- Gloria Wheeler 'E'3,652 mcf last 12 months
- Forrest Wheeler 'A'1,662 bbl last 12 months
- Hardin-Rayes A11,803 bbl last 12 months
- Berta Unit1,715 bbl last 12 months
- Moczygemba1,804 bbl last 12 months
- Gawlik B1,805 bbl last 12 months
Leases within 10 km
- Jea Unit VII Las3,993 bbl last 12 months · 0 km
- Jea Hc36 Las G28,526 bbl last 12 months · 0.3 km
- Jea Hc9 Las G211,128 bbl last 12 months · 0.3 km
- Jea Unit IV Las4,288 bbl last 12 months · 0.6 km
- Jea Unit L Las19,805 bbl last 12 months · 0.7 km
- Jea Unit II Las2,970 bbl last 12 months · 1.4 km
- Jea Hc5 Las8,319 bbl last 12 months · 1.5 km
- Jea Hc6 Las10,255 bbl last 12 months · 1.5 km
- Jea Unit X Las2,980 bbl last 12 months · 1.5 km
- Jea Hc4 Las9,397 bbl last 12 months · 1.5 km
Drilling permits within 10 km
- CONNELL AVANT #A 1Hnew drill · horizontal · Rosewood Resources, Inc. · Nov 2, 2026 · 9.3 km
- CONNELL AVANT #A 2Hnew drill · horizontal · Rosewood Resources, Inc. · Nov 2, 2026 · 9.3 km
- CONNELL AVANT #A 3Hnew drill · horizontal · Rosewood Resources, Inc. · Nov 2, 2026 · 9.4 km
- FLORES #3Hnew drill · horizontal · Silver Hill Energy Operating LLC · Aug 11, 2026 · 8 km
- FLORES #4Hnew drill · horizontal · Silver Hill Energy Operating LLC · Aug 11, 2026 · 8 km
Where it sits
This county
Where this page comes from
- Railroad Commission of Texas production, permits, wells
- U.S. Energy Information Administration prices
How this page is made
Our software builds this page from the public records above. Every figure on it is computed from them, and the page is rebuilt when a source publishes a new month or a new roll. Where the page has a written summary, our software writes it from the page's own figures, and it is checked against them before it goes up. Royalty Clerk is run by AGI Solutions LLC; no operator pays for a page or sees one first.